Quabbin Facts and Figures
| Reservoir & Watershed | Winsor Dam | Spillway | Goodnough Dike | Water Supply |
| Costs | Quabbin Park | Historical | Forestry | Wildlife |
Reservoir and Watershed
| Reservoir length | 18 miles |
| Reservoir depth (max) | 151 feet |
| Reservoir depth (avg) | 45 feet |
| Shoreline (without islands) | 118 miles |
| Island shoreline | 63 miles |
| Reservoir capacity | 412 billion gallons |
| Reservoir surface area | 25,000 acres |
| Top one inch when full | 750 million gallons |
| Area of watershed | 120,000 acres |
| Area of Prescott Peninsula | 12,300 acres |
| Area of islands | 3,500 acres |
| Highest watershed elevation (Prospect Hill, Phillipston) | 1,383 feet |
| Reservoir elevation when full, Boston City base (BCB) | 530 feet |
| Towns in watershed | Athol, Barre, Belchertown, Hardwick, New Salem, Orange, Pelham, Petersham, Phillipston, Shutesbury, Ware, Wendell |
| Swift River release (legal requirement) | 20 million gallons/day |
| Average annual precipitation | 44 inches |
| Average precipitation yield to reservoir | 50% |
| Average reservoir gain from 1 inch precipitation | 1.6 billion gallons |
Winsor Dam
| Built | 1935-1939 |
| Length | 2,640 feet |
| Maximum height above bedrock | 295 feet |
| Height above Swift River | 170 feet |
| Fill used | 4 million cubic yards |
| Width at top / bottom | 35 feet / 724 feet |
| Number of caissons | 40 |
Winsor Dam Spillway
| Length | 400 feet |
| Height | 4-15 feet |
| Width | 7-12 feet |
| Height above riverbed | 155 feet |
Goodnough Dike
| Built | 1933-38 |
| Length | 2,140 feet |
| Width top / bottom | 35 feet / 878 feet |
| Height above bedrock | 264 feet |
| Height above Beaver Brook | 135 feet |
| Fill used | 2.5 million cubic yards |
| Number of caissons | 31 |
Water Supply
| Lowest safe level | -40' (38% capacity) |
| Lowest historic level (3/5/67) | -34.3' (45% capacity) |
| Highest historic level (6/1/84) | +1.8' (103% capacity) |
| Number of years over spillway | 16 |
| Daily safe yield (entire MDC system) | 300 million gallons |
| Population served 1946 1963 1990 | 1.5 million 2.1 million 2.2 million |
| Per capita use (includes industrial) 1950 1963 1980 1990 | 104 gallons/day 138 gallons/day 177 gallons/day 151 gallons/day |
Costs
| Acquisition of real estate | $9.6 million |
| Construction of Winsor Dam | $5.85 million |
| Construction of Goodnough Dike | $2.9 million |
| Relocation work | $1.39 million |
| Reforestation work | $135,000 |
| 1936 Clearing Project | $1.84 million |
| Quabbin Park Cemetery | $266,000 |
| Total Project Costs | $53 million |
| Lives lost during construction | 26 |
Quabbin Park
| Opened to public | July 1945 |
| Administration Building built | 1938-39 |
| Visitor Center opened | 1984 |
| Size | 3,200 acres |
| Public roads | 12 miles |
| Trails | 22 miles |
| Quabbin Hill Lookout Tower Built Height Elevation at base States seen Sight distance (Mt. Greylock) | 1940-41 84 feet 1,033 feet MA, NH, CT 62 miles |
| Quabbin Park Cemetery Built Remains transferred Total grave sites (1990) Size Developed area | 1931-32 6,601 7,971 82 acres 22 acres |
| Winsor Memorial Dedicated Rededicated | 6/17/41 6/16/88 |
Historical
| Date towns discontinued | April 28, 1938 |
| Number of structures removed | 1,100 |
| Number of homes removed | 650 |
| Population displaced | 2,500 |
| Highways abandoned | 242 miles |
| Highways relocated | 36 miles |
| Railroad tracks removed | 31.5 miles |
| Number of cemeteries removed | 34 |
| Grave sites removed | 7,613 |
| Size of original taking | 80,443 acres |
| Average cost per acre | $108 |
Forestry
| Seedlings planted 1936-46 | 8.2 million |
| Number of native-tree species | 70+ |
| Hardwood forest cover | 67% |
| Softwood forest cover | 33% |
| Forest cover types Timber - 60-100+ years old Poles - 40-60 years old Seedling & sapling Fields | 66% 33% <1% <1% |
| Gravel roads in Quabbin Reservation | 250 miles |
| Annual seedling plantings | 40,000 trees |
Wildlife
| Bird species total / confirmed nesting | 250+ / 120+ |
| First recorded Loon nesting | 1975 |
| Bald Eagle First recorded Introduction Program Number of birds released First successful nest Maximum recorded in a season Cost of program | 1948 1982-88 41 1989 42 $210,000 |
| Mammal species | 50 |
| Fish species | 27 |
| First Coyote seen | 1971 |
| Amphibian species | 19 |
| Reptile species | 15 |